← all projects

Approx. 850 MW CCGT Unit at Blachownia Power Plant (Elektrownia Blachownia Nowa, KGHM/TAURON, abandoned)

cancelledstage: announcedabandoned
PLN 3.5 billion
programme budget (multi-year) · data from 2012net or gross: not recorded≈ PLN 3.5 billion (value-by-stage, est., nominal)planned funding: the investor’s own funds, other sources

Elektrownia Blachownia Nowa Sp. z o.o. was a special-purpose vehicle established on 5 September 2012 by KGHM Polska Miedź S.A. and TAURON Wytwarzanie S.A. (a subsidiary of TAURON Polska Energia), each holding a 50% stake, for the purpose of building a CCGT (combined-cycle gas turbine) unit of approximately 850 MW at the site of Blachownia Power Plant in Kędzierzyn-Koźle (Opole Voivodeship). The estimated total outlay for the investment was put at approximately PLN 3.5 billion, and the unit was to be commissioned in 2017. On 30 December 2013, KGHM Polska Miedź S.A. together with TAURON Polska Energia S.A. and TAURON Wytwarzanie S.A. signed an agreement to temporarily suspend the project, citing the current situation on the electricity and gas markets, which was increasing investment risk, and the need to review and optimise the project. On 28 July 2016, the partners terminated the 30 December 2013 agreement and decided to proceed with liquidating the company. The unit was never built.

Why it failed

KGHM Polska Miedź S.A. and TAURON Wytwarzanie S.A. established the special-purpose vehicle Elektrownia Blachownia Nowa Sp. z o.o. on 5 September 2012 (each holding a 50% stake) to build a CCGT unit of approximately 850 MW, with estimated outlays of around PLN 3.5 billion and a planned commissioning date of 2017. On 30 December 2013, the partners signed an agreement to temporarily suspend the project, citing the situation on the electricity and gas markets, which was increasing investment risk. On 28 July 2016, the parties terminated the 2013 agreement and decided to proceed with liquidating the company. The unit was never built.

How it went

Assessment: settled, as of 28 Jul 2016. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet. How to read this section

Deliverynot delivered[4]
Utilisationnot operational[3]

Timeline

  1. Announced5 Sep 2012
  2. Original date2017

Change history

  • 28 Jul 2016status: cancelledRozwiązanie porozumienia z 2013 r. i decyzja o przystąpieniu do likwidacji spółki; blok nie został wybudowany.
  • 30 Dec 2013status: pausedPorozumienie o czasowym zawieszeniu realizacji projektu z powodu sytuacji na rynku energii elektrycznej i gazu.
  • 5 Sep 2012status: plannedZawiązanie spółki celowej Elektrownia Blachownia Nowa przez KGHM i TAURON Wytwarzanie (po 50% udziałów).
  • 5 Sep 2012stage: announced

Significance

The project envisaged building one of the larger CCGT units in Poland (approximately 850 MW) through a special-purpose vehicle owned by two State Treasury companies, KGHM Polska Miedź and the TAURON group. The investment, with an estimated value of approximately PLN 3.5 billion, was first suspended (2013) and then abandoned along with the liquidation of the special-purpose vehicle (2016), against a backdrop of deteriorating market conditions for gas-fired power generation. The unit was never built.

Sources 6 · 5 independent · 3 archived

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Biuro prasowe TAURON Polska Energia S.A.Sep 2012
    CostAnnouncedOriginal dateInvestorFunding
    Costszacowane łączne nakłady na inwestycje wyniosą około 3,5 mld zł
    AnnouncedKGHM Polska Miedź oraz TAURON Wytwarzanie, spółka zależna TAURON Polska Energia, zawiązały 5 września spółkę celową pod nazwą Elektrownia Blachownia Nowa.year taken from the source's publication date (Sep 2012)
    Original dateblok zostanie przekazany do eksploatacji w 2017 roku
    InvestorWspólnicy objęli po 50 proc. udziałów w kapitale zakładowym spółki
    FundingPrzedsięwzięcie zostanie sfinansowane ze środków własnych partnerów oraz kredytu zaciągniętego przez nową spółkę.
  2. Forsal.pl30 Dec 2013
    Stage
    Stagepodpisały porozumienie, na mocy którego postanowiono o czasowym zawieszeniu realizacji projektu budowy bloku gazowo-parowego
  3. Forsal.pl28 Jul 2016
    StatusFailure descriptionUtilisation
    StatusKGHM Polska Miedź S.A. oraz Tauron Wytwarzanie S.A., zgodnie postanawiają, że przystąpią do likwidacji spółki
    Failure descriptionStrony zgodnie postanawiają rozwiązać łączące je porozumienie z dnia 30 grudnia 2013 r.
    UtilisationKGHM Polska Miedź oraz Tauron Wytwarzanie - spółka zależna od Tauron Polska Energia - odstąpiły od realizacji projektu budowy bloku gazowo-parowego i przystąpią do likwidacji spółki "Elektrownia Blachownia Nowa", podały Tauron i KGHM.
  4. wnp.pl (Portal Gospodarczy)28 Jul 2016
    StatusDelivery
    Status · DeliverySpółki Tauron Polska Energia, KGHM Polska Miedź oraz Tauron Wytwarzanie podpisały 28 lipca br. porozumienie na mocy którego zgodnie postanowiły odstąpić od realizacji projektu budowy bloku gazowo-parowego w Elektrowni Blachownia Nowa.
  5. Bankier.pl20 Jun 2013
    InvestorCostOriginal date
    InvestorSpółkę Elektrownia Blachownia Nowa, która miałaby zrealizować to przedsięwzięcie, KGHM i Tauron zawiązały we wrześniu ub. roku.
    Cost · Original dateZgodnie z ówczesnymi szacunkami, nakłady na inwestycję miałyby sięgnąć ok. 3,5 mld zł, a nowy blok mógłby zostać przekazany do eksploatacji w drugim kwartale 2017 r.
  6. Elektroinzynieria.pl25 Jun 2013
    CostOriginal date
    Cost · Original dateJak wtedy szacowano, nakłady na inwestycję mogłyby wynieść ok. 3,5 mld zł, a nowa jednostka mogłaby rozpocząć pracę w drugim kwartale 2017 r.