Dolna Odra Combined-Cycle Gas Units (Gryfino) – 2x ~700 MW

completedstage: operationaldelivereddelayed
PLN 4.7 billion
contract value · data from 2024net of VAT≈ PLN 4.7 billion (value-by-stage, est., nominal)funding: capacity market

The construction of two combined-cycle gas (CCGT) units, no. 9 and no. 10, at the Dolna Odra Power Plant Complex in Nowe Czarnowo near Gryfino (Zachodniopomorskie Voivodeship), belonging to PGE Górnictwo i Energetyka Konwencjonalna of the PGE Group. Each unit has a rated gross electrical capacity of 683 MWe, for a total of approximately 1,366 MW of new gas-fired capacity. The investment was carried out by a consortium of General Electric (GE Vernova) as leader and Polimex Mostostal. Unit no. 9 was handed over for operation in August 2024, and unit no. 10 at the end of October 2024 – with a significant delay relative to the original deadline of December 2023.

How it went

Assessment: provisional, as of 15 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one carries no assessment yet. How to read this section

Deliverydelivered[7]
Scheduledelayed[4]
Utilisationin use[6]
gross electricity production (H1 2025)
Current
2,13 TWh w I półroczu 2025 (ok. 36% współczynnika wykorzystania mocy) (H1 2025)
Capacity or target
moc 1366 MW; ~5,9 TWh przy teoretycznie pełnym obciążeniu w 6 miesięcy; pokrycie >5% krajowego zapotrzebowania na energię elektryczną

Timeline

Slip: +10 mo. vs. the original date

  1. Original date11 Dec 2023
  2. Delivery29 Oct 2024

Change history

  • 29 Oct 2024stage: operational
  • 14 Aug 2024stage: commissioning

Significance

The two combined-cycle gas units with a total capacity of approximately 1,366 MW replaced part of the aging coal-fired generating capacity and made the Dolna Odra power plant the largest gas-fired power plant in Poland. The investment strengthens security of energy supply in north-western Poland and provides flexible, dispatchable capacity balancing the growing share of renewable sources in the national power system.

Sources 8 · 6 independent · 6 archived

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.

  1. WNP.plAug 2024
    StatusStage historyDelivery
    Status · Stage history · Delivery14 sierpnia 2024 r. przekazały do eksploatacji blok gazowo-parowy nr 9The sentence is about unit 9; both units were put into operation on 29 October 2024.
  2. elektro.infoAug 2024
    Investor
    InvestorNowym Czarnowie koło Gryfina (woj. zachodniopomorskie), należącej do Grupy PGE
    LocationNowym Czarnowie koło Gryfina (woj. zachodniopomorskie)
  3. Wikipedia (pl)
    StatusStageDeliveryStage history
    Status · Delivery · Stage historyNa 30 września 2024 zaplanowano przekazanie do eksploatacji bloku nr 10[15], ostatecznie całość oddano do użytku 29 października 2024[10].
    Stage29 października – oddanie do użytku bloku gazowego nr 10
  4. Interia BiznesAug 2024
    CostOriginal dateSchedule
    CostŁączna wartość wszystkich zawartych umów wyniosła około 4,73 mld zł netto - czyli prawie 5,82 mld zł brutto.
    Original dateplanowano, że inwestycja zostanie ukończona cztery lata później - 11 grudnia 2023 r.
    SchedulePo kilku miesiącach opóźnień ruszył duży blok gazowy w elektrowni Dolna Odra. Początkowo miał być oddany w grudniu ubiegłego roku, jednak termin ten był przesuwany dwukrotnie.
  5. PGE GiEK (Zespół Elektrowni Dolna Odra)30 Jan 2020
  6. WNP.plMar 2026
    Utilisation
    UtilisationW I półroczu 2025 PGE Gryfino Dolna Odra wyprodukowała 2,13 TWh energii elektrycznej.
  7. Teraz ŚrodowiskoOct 2024
    UtilisationFundingStatusDelivery
    Utilisation · FundingInstalacja posiada obowiązujący od 2024 r. 17-letni kontrakt na aukcji rynku mocy
    Status · DeliveryOddanie elektrowni do eksploatacji przez PGE Polską Grupę Energetyczną nastąpiło 29 października br.