Expansion of the Wierzchowice Underground Gas Storage Facility to 1.2 bcm
The expansion of the Wierzchowice Underground Gas Storage (PMG) Facility, the largest underground natural gas storage facility in Poland, operating in a depleted gas field since 1995, consisted of doubling the facility's active capacity from just under 575 million m³ to approximately 1.2 billion m³. On 3 October 2008, PGNiG SA selected the contractor: a consortium including PBG SA (leader), the Italian company Tecnimont S.p.A., the French company Sofregaz, and the Czech companies Plynostav Pardubice Holding and Plynostav – Regulace Plynu. The works were to take three years and be completed by November 2011, with the storage facility's commissioning planned for early 2012. The investment received EU co-financing of approximately PLN 503.6 million, and the planned total implementation cost was estimated at PLN 1.96 billion gross (the value of the contract with the contractor alone was approximately PLN 1.1 billion net, i.e. approximately PLN 1.3 billion gross). Implementation encountered serious problems (including the bankruptcy of the consortium leader PBG) and suffered a multi-year delay; the expanded facility began operating on 17 March 2015. The owner and investor is PGNiG SA.
How it went
Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one carries no assessment yet. How to read this section
- Current
- ok. 1,2 mld m3 (eksploatacja od 17.03.2015)
- Capacity or target
- ok. 1,2 mld m3
Timeline
Slip: +40 mo. vs. the original date
- Original dateNov 2011
- Delivery17 Mar 2015
Significance
The expansion made the Wierzchowice PMG the largest underground natural gas storage facility in Poland, doubling its active capacity from just under 575 million m³ to approximately 1.2 billion m³. The increase in national gas storage capacity was part of building the country's energy security and its ability to balance seasonal fluctuations in consumption and supply disruptions; the project received EU support. The investment also became one of the notable examples of contractor delays in the Polish energy sector following the bankruptcy of the consortium leader PBG.
Sources 5 · 4 independent · 1 archived
Every fact on this card comes from the sources below. Next to each source – which fields it supports.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- WNP.pl2013Original dateInvestorSchedule
Original datePrace miały potrwać trzy lata. Inwestycja miała zostać zakończona w listopadzie 2011 roku.
InvestorPGNiG wybrało konsorcjum z udziałem PBG na wykonawcę rozbudowy podziemnego magazynu gazu
ScheduleRozbudowa Podziemnego Magazynu Gazu Wierzchowice miała się zakończyć w listopadzie 2011 roku. Niemal z półtorarocznym opóźnieniem prace powoli zmierzają ku zakończeniu, bo projekt jest już zaawansowany w 97 proc.
- Money.pl6 Oct 2010Cost
CostPlanowany całkowity koszt realizacji to 1,96 mld zł brutto.
- [3]Budowa Podziemnego Magazynu Gazu Wierzchowice - Inwestycje Energetyczne (Politechnika Warszawska) ↗Politechnika WarszawskaStatusStageDeliveryUtilisation
Status · Stage · Delivery · UtilisationData rozpoczęcia eksploatacji: 17.03.2015
- Money.pl / PAP16 Feb 2011
- Funding
Fundingdofinansowanie z UE 484 557 817,61 zł