← all projects

460 MW power generating unit (supercritical CFB) at Łagisza Power Station

completedstage: operationaldelivered
PLN 1.9 billion
estimate · data from 2009net or gross: not recorded≈ PLN 1.9 billion (value-by-stage, est., nominal)funding: the investor’s own funds, state special fund, private finance

The 460 MW unit at the Łagisza Power Station in Będzin (Łagisza district) was the world's first power generating unit with a CFB boiler (circulating fluidised bed) operating at supercritical parameters. The boiler was supplied by Foster Wheeler. The foundation stone was laid and the construction site consecrated on 12 May 2006, and the handover-to-service protocol for the unit was signed on 27 June 2009. The investor was Południowy Koncern Energetyczny S.A. (now TAURON Wytwarzanie S.A.). Ranked among the largest investments in the Polish power sector, it cost around PLN 2 billion, though construction was completed below the planned budget, at a cost of around PLN 1.9 billion. The unit is fired with hard coal and achieves a gross efficiency of no less than 45%.

How it went

Assessment: settled, as of 2009. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one carries no assessment yet. How to read this section

Deliverydelivered[4]
Budgetunder budget[3]
Utilisationin use[2]
eksploatacja bloku wytwórczego 460 MW
Current
blok przekazany do eksploatacji 27 czerwca 2009 r. i pracujący w Elektrowni Łagisza
Capacity or target
460 MW

Timeline

  1. Construction start12 May 2006
  2. Delivery27 Jun 2009

Significance

The 460 MW unit at Łagisza was the world's first power generating unit fitted with a CFB fluidised-bed boiler operating at supercritical parameters, making it a model, reference installation for this technology in coal-fired power generation. Its high efficiency (no less than 45% gross) and its ability to burn hard coal, coal sludge and biomass reduced fuel consumption and emissions compared with older units. The investment was one of the largest in the Polish power sector during this period.

Sources 4 · 3 independent · 2 archived

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Wikipedia (pl)
    StatusStageConstruction startInvestor
    Status · StageBlok został przekazany do eksploatacji 30 czerwca 2009 r.Wikipedia gives 30 June; wnp.pl and PAP of 29 June 2009 date the handover protocol to 27 June, and the record follows them.
    Construction start12 maja 2006 wmurowano akt erekcyjny i poświęcono plac budowy nowego bloku
    InvestorW dniu 20 stycznia 2020 TAURON Wytwarzanie S.A. poinformował, że dostosował kosztem 120 mln zł blok 460 MWe do wytwarzania ciepła grzewczego dla Zagłębia Dąbrowskiego
  2. money.pl / PAP29 Jun 2009
    InvestorFundingUtilisationStatusStageDelivery
    Investornależącej do Południowego Koncernu Energetycznego Elektrowni Łagisza w Będzinie
    FundingInwestycja była finansowana ze środków własnych PKE, pożyczek funduszy ekologicznych oraz ze środków pochodzących z emisji obligacji.
    UtilisationO pomyślnym zakończeniu trwającego 720 godzin ruchu próbnego i formalnym przekazaniu nowego bloku do eksploatacji poinformował w poniedziałek Dariusz Wójcik z PKE. Podpisanie stosownego protokołu oznacza, że blok o mocy 460 megawatów może w pełni służyć produkcji prądu.
    Status · Stage · DeliveryO pomyślnym zakończeniu trwającego 720 godzin ruchu próbnego i formalnym przekazaniu nowego bloku do eksploatacji poinformował w poniedziałek Dariusz Wójcik z PKE.
  3. netTG.pl
    CostBudget
    Cost · Budgetbudowę zamknięto poniżej planowanego budżetu, kosztem ok. 1,9 mld zł
  4. WNP.PL (Wirtualny Nowy Przemysł) – portal gospodarczy29 Jun 2009
    StatusStageDelivery
    Status · Stage · DeliveryW należącej do Południowego Koncernu Energetycznego Elektrowni Łagisza 27 czerwca podpisano protokół przekazania do eksploatacji bloku 460 MW.year taken from the source's publication date (29 Jun 2009)