← all projects
Energystrategic

LitPol Link (the power bridge): 400 kV Poland–Lithuania electricity interconnection, Ełk–Olita/Alytus

completedstage: operationaldelivered
PLN 2.1 billion
programme budget (multi-year) · data from 2016net or gross: not recorded≈ PLN 2.1 billion (value-by-stage, est., nominal)funding: EU funds, the investor’s own funds

LitPol Link is a cross-border 400 kV electricity interconnection between Poland and Lithuania (on the Ełk–Olita/Alytus route), the first synchronous connection between the Lithuanian power system and the system of continental Western Europe, and an element in ending the so-called energy island status of the Baltic states. The interconnection allows the transmission of 500 MW of electricity; at the Alytus substation a DC insert (a back-to-back converter) was built to link systems operating at different frequencies. The international coordinator of the preparatory and construction works was the LitPol Link company, established in 2008 by the transmission system operators Polskie Sieci Elektroenergetyczne (PSE) and the Lithuanian Litgrid. Construction of the section on the Lithuanian side (in the Alytus area) began on 5 May 2014, and the interconnection was put into service on 9 December 2015. On the Polish side, as part of the project PSE built four power lines with a total current-circuit length of 602.2 km and five electricity substations, and expanded two further substations. According to an audit by the Supreme Audit Office (NIK), the total cost of preparing and implementing the Poland–Lithuania power bridge project was PLN 2,139,758.4 thousand (against a planned PLN 2,706,709 thousand), of which co-financing from the Operational Programme Infrastructure and Environment 2007–2013 and the Trans-European Energy Networks programme amounted to PLN 904,409.5 thousand.

How it went

Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one has an assessment with no confirmed quote. How to read this section

Deliverydelivered[1]
Budgetunder budget[2]
Utilisationin use[2]

A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.

zdolność przesyłowa połączenia
Current
eksploatacja połączenia 400 kV Polska–Litwa o mocy 500 MW od 9 grudnia 2015 r.
Capacity or target
500 MW

Timeline

  1. Construction start5 May 2014
  2. Delivery9 Dec 2015

Significance

LitPol Link was the first electricity interconnection between Poland and Lithuania and a key element in ending the energy isolation of the Baltic states (the so-called energy island) as part of the Baltic Energy Market Interconnection Plan (BEMIP). It enabled the transmission of 500 MW of electricity, increased the energy security of north-eastern Poland, and created the infrastructural basis for the later synchronisation of the Baltic systems with the continental European system. The Supreme Audit Office (NIK) assessed that the first stage of the project was completed on schedule and within the planned costs, achieving its planned objectives.

Sources 5 · 4 independent · 4 archived

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.

  1. Wikipedia (en)
    StatusStageConstruction startDeliveryInvestor
    Status · Stage · DeliveryLitPol electricity link started operations on 9 December 2015
    Construction startConstruction of the link commenced in the Alytus district on 5 May 2014.
    InvestorLitPol Link was founded by PSE and Litgrid with equal stakes.
  2. Najwyższa Izba Kontroli (NIK)2016P/16/014/KGP
    CostFundingBudgetUtilisation
    Cost · BudgetCałkowity koszt przygotowania i realizacji projektu mostu elektroenergetycznego Polska-Litwa wyniósł 2139758,4 tys. zł (planowano 2706709 tys. zł)
    Fundingkwota dofinansowania ze środków Programu Operacyjnego Infrastruktura i Środowisko 2007-2013 oraz Programu Transeuropejskie Sieci Energetyczne wyniosła 904409,5 tys. zł
    UtilisationPo pierwszych miesiącach funkcjonowania mostu przesył energii elektrycznej z Litwy do Polski trzykrotnie przewyższał przesył w przeciwnym kierunku.
  3. Litgrid / EPSO-G
  4. Money.pl2016
  5. Funding
    FundingPonad dwieście milionów euro pochodzić będzie z Programu Operacyjnego Infrastruktura i Środowisko na lata 2007-2013. Pozostałe finansowanie zapewni polski operator