← all projects
Energystrategic

Opole Power Plant – Units 5 and 6 (2×900 MW, hard coal)

completedstage: operational
PLN 9.4 billion
contract value · data from 2012net or gross: not recorded≈ PLN 9.4 billion (value-by-stage, est., nominal)

Expansion of the grid-scale Opole Power Plant in Brzezie near Dobrzeń Wielki with two new supercritical hard-coal-fired units with a rated capacity of 2×900 MWe (around 1,800 MW combined). The management board of PGE Elektrownia Opole SA signed the contract for the construction of Units 5 and 6 on 15 February 2012 with a consortium of RAFAKO SA, POLIMEX-MOSTOSTAL SA and MOSTOSTAL WARSZAWA SA (the general designer and supplier of key equipment was GE Power, formerly Alstom Power); the net value of the contract was PLN 9,397,000,000 (PLN 11,558,310,000 gross). The order to start works was issued on 31 January 2014, and construction began on 15 February 2014. Unit 5, with a capacity of 900 MW, was handed over for operation on 31 May 2019, and Unit 6 on 30 September 2019; the official completion of construction was announced on 10 October 2019. The investor was PGE Górnictwo i Energetyka Konwencjonalna S.A. (PGE GiEK), and the units operate as part of the Opole Power Plant branch. It was the largest investment of its kind in Poland since 1989.

How it went

We have assessed this project, but none of the four axes is shown here: 2 carry no assessment yet, 2 have an assessment with no confirmed quote. The timeline and sources below show what is known about it. How to read this section

Timeline

  1. Construction start15 Feb 2014
  2. Delivery2019

Change history

  • 10 Oct 2019status: completedOficjalne ogłoszenie zakończenia budowy bloków 5 i 6 Elektrowni Opole.
  • 30 Sep 2019stage: operational
  • 31 May 2019stage: operational
  • 15 Feb 2014stage: construction

Significance

The construction of Units 5 and 6 at the Opole Power Plant (2×900 MW, around 1,800 MW combined) was the largest investment of its kind in Poland since 1989 and the largest investment in the Polish power sector during that period. After the new units were commissioned, the Opole Power Plant could cover around 8 per cent of national electricity demand, substantially strengthening the security of power supply in the National Power System. The investment was carried out by a Polish contracting consortium (RAFAKO, Polimex-Mostostal, Mostostal Warszawa) and was of major importance for the domestic power industry and the Opole region.

Sources 4 · 4 independent · 2 archived

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Ministerstwo Aktywów Państwowych (gov.pl)10 Oct 2019
  2. WNP.pl10 Oct 2019
    StatusDelivery
    Status10 października 2019 r. nastąpiło oficjalne oddanie do eksploatacji bloku nr 6 w Elektrowni Opole. To oznacza, że dobiegła końca rozbudowa opolskiej elektrowni o dwie nowe jednostki o łącznej mocy 1800 MW.
    Delivery10 października 2019 r. nastąpiło oficjalne oddanie do eksploatacji bloku nr 6 w Elektrowni Opole.
  3. Politechnika Warszawska – Inwestycje energetyczne w Polsce
    StageCostConstruction start
    Stage31 maja 2019 - blok o mocy 900 MW został przekazany do eksploatacji
    Stage30 września 2019 - blok nr 6 został przekazany do eksploatacji
    Costwartość netto umowy wynosi 9.397.000.000 zł (11.558.310.000 zł brutto)
    Construction startPolecenia rozpoczęcia prac wydano 31 stycznia 2014r., prace ruszyły 15 lutego 2014r.
  4. Główny Mechanik14 Oct 2019
    Investor
    InvestorOddajemy naszym gospodarzom PGE Górnictwo i Energetyka Konwencjonalna dwa nowe bloki energetyczne o imponującej mocy ponad 910 MW każdy.