New power unit no. 11 (496 MW) at Turów Power Plant

completedstage: operationaldelivereddelayed
PLN 3.6 billion
contract value · data from 2014net or gross: not recorded≈ PLN 3.6 billion (value-by-stage, est., nominal)

A new power unit no. 11 with a gross capacity of 496 MW at the Turów Power Plant (Bogatynia, Dolnośląskie voivodeship), owned by PGE Górnictwo i Energetyka Konwencjonalna S.A. (PGE GiEK). The unit is fired with lignite from the nearby Turów mine and operates at supercritical parameters, achieving an electricity-generation efficiency of over 43 per cent. It replaced the three oldest units (nos. 8, 9 and 10). PGE GiEK signed the construction contract in 2014, and it was carried out by a consortium of Mitsubishi Hitachi Power Systems Europe GmbH (leader, 55.38 per cent share), Budimex SA (22.31 per cent) and Técnicas Reunidas SA (22.31 per cent). Construction work began in December 2014, the foundation stone was laid on 29 June 2016, the unit was first synchronised with the National Power System on 21 December 2020, and it was officially commissioned on 14 May 2021. This was the last investment in the PGE Group involving the construction of a conventional fossil-fuel-fired power unit.

How it went

Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one carries no assessment yet, one has an assessment with no confirmed quote. How to read this section

Deliverydelivered[4]
Scheduledelayed[2]

Timeline

  1. Construction startDec 2014
  2. Delivery14 May 2021

Significance

Unit no. 11, with a capacity of 496 MW, was the last investment in the PGE Group involving the construction of a conventional fossil-fuel-fired power unit. It replaced the three oldest units of the Turów Power Plant (nos. 8, 9 and 10), using the latest technologies: operation at supercritical parameters and an electricity-generation efficiency of over 43 per cent, which significantly reduces CO2 emissions compared with older-generation units.

Sources 4 · 3 independent · 2 archived

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Budimex SA
    Cost
    CostWartość kontraktu 3,646 mld PLN
  2. Politechnika Warszawska
    Construction startSchedule
    Construction start01.12.2014 r. Konsorcjum wykonawców bloku otrzymało Polecenie Rozpoczęcia Prac.
    Schedule28.07.2020 – PGE poinformowało, że wykonawca bloku zaproponował nowy termin zakończenia bloku jako 30 kwietnia 2021 roku. Poprzednia data zakończenia to był 31 październik 2020 roku.
  3. Wikipedia (pl)
  4. WNP.pl2021
    StatusStageDeliveryInvestor
    Status · Stage · DeliveryNastąpiło oficjalne przekazanie do eksploatacji bloku energetycznego o mocy 496 MW
    DeliveryOficjalne przekazanie do eksploatacji bloku energetycznego o mocy 496 MW w Elektrowni Turów nastąpiło 14 maja 2021 roku.
    InvestorElektrowni Turów, należącej do spółki PGE Górnictwo i Energetyka Konwencjonalna (PGE GiEK)