A1 motorway Sośnica (Gliwice) – Gorzyczki (the Silesian A1 section, via Świerklany)
The Silesian, southern section of the A1 motorway from the Sośnica interchange in Gliwice (connection with the A4 motorway) to the state border with the Czech Republic at Gorzyczki, with a total length of approximately 48 km, carried out by the General Directorate for National Roads and Motorways (GDDKiA) with co-financing from the EU Cohesion Fund. The investment was divided into three sections corresponding to three siting decisions of the Silesian voivode: Sośnica–Bełk (15.4 km), Bełk–Świerklany (14.5 km), and Świerklany–state border at Gorzyczki (18.3 km). The northern Sośnica–Bełk section was carried out under Stage I (total eligible project cost EUR 233.5 million, Cohesion Fund grant EUR 193.8 million, EC decision C(2004)5577) and opened to traffic on 23 December 2009; its first fragment, Sośnica–Rybnik (15.4 km), cost PLN 827 million (EUR 208 million). The Bełk–Gorzyczki sections made up Stage II (total eligible cost EUR 339.9 million, Cohesion Fund grant EUR 224.4 million); the Bełk–Świerklany contract, worth EUR 285.2 million, was signed on 7 August 2008 with the STRABAG / HEILIT+WOERNER consortium. On 30 November 2012 the section closing the route to the state border was opened to passenger traffic (with a temporary detour via voivodeship roads near the Mszana viaduct); a full, continuous A1 on this section was achieved after the opening of the Świerklany–Mszana fragment on 23 May 2014. The cost figure in this record is our own sum of the eligible costs of both stages (Stage I EUR 233.5 million plus Stage II EUR 339.9 million, approximately EUR 573.4 million), converted into zloty at the 2006 average annual NBP EUR/PLN exchange rate (approximately 3.8951). This is a derived figure combining two EU decisions from 2004 and 2006; the base price year (price_year 2006) was adopted following the dominant Stage II decision and is approximate.
How it went
Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet, one has an assessment with no confirmed quote. How to read this section
Timeline
- Construction start2007
- Delivery30 Nov 2012
Change history
- 30 Nov 2012status: completedOddanie do ruchu osobowego odcinka domykającego A1 do granicy państwa w Gorzyczkach (Etap II); ciągły przekrój uzyskano po otwarciu fragmentu Świerklany–Mszana 23 maja 2014 r.
- 30 Nov 2012stage: operational
- 23 Dec 2009stage: operational
Significance
The Silesian A1 section Sośnica–Gorzyczki closed the motorway connection between the Upper Silesian agglomeration and the state border with the Czech Republic (the Gorzyczki–Věřňovice crossing) and forms part of the trans-European north-south corridor (TEN-T) running from Gdańsk towards southern Europe. The Sośnica interchange, where the A1 crosses the A4, is one of the largest motorway interchanges in Poland. The investment was one of the largest road projects co-financed by the Cohesion Fund in the Silesian Voivodeship.
Sources 5 · 3 independent · 5 archived
Every fact on this card comes from the sources below. Next to each source – which fields it supports.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- GDDKiA (serwis archiwalny)Status
StatusW dniu 23.12.2009 r. przedmiotowy odcinek autostrady został oddany do ruchu
- [2]Budowa autostrady A-1, odcinek Sośnica (Gliwice) – granica państwa (Gorzyczki), Etap II: Bełk – Gorzyczki ↗archived ✓GDDKiA (serwis archiwalny)StageDeliveryInvestorCostFunding
Stage · DeliveryW dniu 30 listopada 2012r. został otwarty dla ruchu osobowego przedmiotowy odcinek autostrady A1
InvestorW dniu 29.12.2009 r. GDDKiA odstąpiła od kontraktu
Cost · FundingCałkowity koszt kwalifikowany projektu: 339,9 mln EUR (w tym grant FS: 224,4 mln EUR)
- Wikipedia (pl)Construction start
Construction startJego budowa rozpoczęła się 26 marca 2007.
- Forsal.pl (Dziennik Gazeta Prawna)23 May 2014
- Interia Motoryzacja22 Dec 2011