A4 Motorway Rzeszów Wschód – Jarosław Zachód

completedstage: operationaldelivered
PLN 986 million
contract value · data from 2014net or gross: not recorded≈ PLN 986 million (value-by-stage, est., nominal)funding: EU funds

The Rzeszów Wschód – Jarosław Zachód section of the A4 motorway, 41.2 km long, in Podkarpackie Voivodeship, was one of the last sections of the longest motorway in Poland (the east-west corridor forming part of the A4 route). The investor was the General Directorate for National Roads and Motorways (GDDKiA), Rzeszów Branch. Construction began under a contract with the Polimex Mostostal S.A. / Doprastav a.s. consortium, signed on 23 September 2010 for PLN 2,195,924,087.54; this contract was terminated on 14 January 2014. The continuation works were carried out by the Budimex S.A. / Strabag Sp. z o.o. consortium under a contract dated 16 September 2014 worth PLN 985,709,828.88 (works began on 30 September 2014). The project built a dual-carriageway motorway together with the Łańcut and Przeworsk interchanges, engineering structures and access roads. The main motorway route was opened to traffic on 20 July 2016 (with sections completed on 31 August 2016 and 20 October 2016).

How it went

Assessment: settled, as of 20 Oct 2016. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet, one has an assessment with no confirmed quote. How to read this section

Deliverydelivered[1]

Timeline

  1. Construction start2010
  2. Delivery2016

Significance

Completion of the Rzeszów Wschód – Jarosław Zachód section closed the A4 motorway route east of Rzeszów and was one of the last sections of the longest motorway in Poland, linking the western border with the eastern one. The construction went through a change of contractor: the original contract with the Polimex Mostostal / Doprastav consortium (2010) was terminated in 2014, and the Budimex / Strabag consortium completed the task, opening the route to traffic in 2016.

Sources 4 · 4 independent · 2 archived

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. GDDKiA (serwis archiwalny)
    StatusStageCostConstruction startDelivery
    Status · Stage · Delivery20.07.2016 - oddanie do użytku trasy głównej autostrady wraz z drogowymi obiektami inżynierskimi
    CostKonsorcjum - Budimex S.A./Strabag Sp z o.o. Wartość: 985 709 828,88 PLN
    Construction startlata realizacji - 2010 – 2016
    Deliveryobecny etap – oddany do użytkowania
  2. Strabag Sp. z o.o.
    Investor
    InvestorGeneralna Dyrekcja Dróg Krajowych i Autostrad Oddział w Rzeszowie
  3. Funding
    Fundingdofinansowanie z UE 2 890 243 728,68 zł
    Fundingprogram Program Operacyjny Infrastruktura i Środowisko działanie VI.1. Rozwój sieci drogowej TEN-T fundusz Fundusz Spójności perspektywa 2007 - 2013