Construction of the tram line to Fordon in Bydgoszcz

completedstage: operationaldelivered
PLN 437 million
programme budget (multi-year) · data from 2016incl. VAT≈ PLN 437 million (value-by-stage, est., nominal)funding: EU funds, local government

The construction of a new tram line connecting the centre of Bydgoszcz with the Fordon district was the largest public-transport investment in the city's history. The new route, about 9.5 km long (with roughly 25 km of track laid in total), was built together with the reconstruction of Bydgoszcz Wschód station, where the construction of a tram viaduct required the railway station to be moved almost 400 m to the west. The investor was the special-purpose company Tramwaj Fordon Sp. z o.o. The construction tender was won by a consortium led by 'Gotowski' Budownictwo Komunikacyjne i Przemysłowe Sp. z o.o. with a bid of PLN 290 million; the construction contract was signed on 22 October 2013. Construction began in 2013 and was completed after two years: the first test run took place on 12 November 2015, and regular passenger service began on 16 January 2016. The investment was linked to the purchase of 12 new five-section, low-floor Swing trams made by Bydgoszcz-based Pesa. The total value of the project as a whole (construction of the line, purchase of rolling stock, reconstruction of Bydgoszcz Wschód station) was PLN 437,308,983.67 gross, including EU co-financing of PLN 209,768,552.18.

How it went

Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one carries no assessment yet, one has an assessment with no confirmed quote. How to read this section

Deliverydelivered[6]
Utilisationin use[6]
eksploatacja linii tramwajowej do Fordonu
Current
regularny ruch pasażerski od 16 stycznia 2016 roku

Timeline

  1. Construction start22 Oct 2013
  2. Original date2015
  3. Delivery16 Jan 2016

Change history

  • 16 Jan 2016stage: operational
  • 22 Oct 2013stage: construction

Significance

The tram line to Fordon was the largest public-transport investment in the history of Bydgoszcz. It connected the large, outlying Fordon district to the rest of the city's tram network with tram track, significantly improving transport links for this part of the city. Construction of the roughly 9.5-kilometre route was linked to the purchase of 12 new low-floor trams and to the reconstruction of Bydgoszcz Wschód railway station, where a tram viaduct was built and the railway station was moved almost 400 m. The project was carried out with EU co-financing (over PLN 209 million).

Sources 7 · 6 independent · 5 archived

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.

  1. Wikipedia (pl)
    StageCostFunding
    StageUruchomienie linii nastąpiło 16 stycznia 2016 roku.
    Cost · FundingWartość całego projektu ogółem (budowa linii, zakup taboru, przebudowa stacji Bydgoszcz Wschód) wyniosła 437 308 983,67 zł brutto, w tym uzyskane dofinansowanie ze środków europejskich 209 768 552,18 zł brutto.
  2. Inżynier Budownictwa
    Investor
    InvestorInwestor: Tramwaj Fordon Sp. z o.o.
  3. Money.pl / PAP
    Original date
    Original datema zostać zrealizowana do końca trzeciego kwartału 2015 r
  4. Prawo.pl20 Aug 2013
  5. TransInfo / InfoTram16 Jan 2014
  6. Zarząd Dróg Miejskich i Komunikacji Publicznej w Bydgoszczy
    StatusConstruction startDeliveryUtilisation
    Status · DeliveryPo odbiorach i pozwoleniu na użytkowanie 16 stycznia 2016 roku na trasę wyjechały pierwsze składy.
    Construction startPodpisanie umowy na budowę odbyło się 22 października 2013 roku
    UtilisationCodziennie z czterech fordońskich linii korzysta już 43 tysięcy pasażerów.
  7. Funding
    FundingBudowa linii tramwajowej do Fordonu zostanie sfinansowana pieniędzmi z obligacji, a nie kredytem z Europejskiego Banku Inwestycyjnego.