S22 Expressway Elbląg – Grzechotki (border with Russia)
The S22 expressway is a 50.6 km route connecting the Elbląg-Wschód interchange (junction with the S7) with the Grzechotki–Mamonowo border crossing on the state border with Russia (Kaliningrad Oblast). It was built in 2006–2008 as a result of rebuilding the former national road No. 22 to expressway standard, carried out by the General Directorate for National Roads and Motorways (GDDKiA) in three implementation sections. The works were carried out by consortia involving, among others, Strabag, Skanska, Warbud, and the Portuguese firms MSF and Teodoro Gomes Alho. Construction works began in 2006, and on 24 September 2008 the entire S22 road was brought into use. According to GDDKiA, the value of the project was PLN 480.3 million; the project was co-financed from European Union funds under the Sectoral Operational Programme Transport (SOP-T). For the related scope, valued at PLN 456,693,086.09, the EU share was given as PLN 323,921,847.82. The route has a single-carriageway cross-section (2/1) with land reserved for a second carriageway. The Grzechotki–Mamonowo border crossing, to which the S22 leads, opened on 3 December 2010.
How it went
Assessment: settled, as of 24 Sep 2008. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet, one has an assessment with no confirmed quote. How to read this section
Timeline
Significance
The S22 expressway forms the final fragment of the road corridor running from the junction with the S7 expressway near Elbląg to the border crossing with Russia (Kaliningrad Oblast) at Grzechotki. The rebuilding of the former national road No. 22 to expressway standard along the 50.6 km section, completed in 2008, improved accessibility to the Grzechotki–Mamonowo border road crossing, opened in December 2010. The route was built as a single carriageway with land reserved for a second carriageway.
Sources 6 · 4 independent · 4 archived
Every fact on this card comes from the sources below. Next to each source – which fields it supports.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.
- GDDKiA (Generalna Dyrekcja Dróg Krajowych i Autostrad)CostConstruction startInvestor
Costwartość projektu: 480,3 mln PLN
Construction startlata realizacji:2006-2008
InvestorZgodnie z prawem ochrony środowiska olsztyński oddział GDDKiA wystąpił pod koniec 2005 r. o wydanie decyzji środowiskowej dla przebudowy drogi krajowej nr 22 na odcinku Elbląg – Grzechotki.
- GDDKiA (Generalna Dyrekcja Dróg Krajowych i Autostrad)Funding
FundingUdział Unii Europejskiej: 323 921 847,82 PLN
- Wikipedia (pl)StatusStageDelivery
Status · Stage24 września cała droga S22 została przekazana do użytku
Delivery31 lipca 2008 zakończono wszelkie prace budowlane[8], a 24 września cała droga S22 została przekazana do użytku[9].
- Funding
FundingKredyt zaciągany jest przez Bank Gospodarstwa Krajowego na rzecz Krajowego Funduszu Drogowego z przeznaczeniem na współfinansowanie 15 inwestycji zawartych w "Programie rzeczowo-finansowym dla inwestycji drogowych realizowanych z wykorzystaniem środków KFD". W ramach "Projektu Modernizacji Dróg w Polsce" ze środków zaciąganego kredytu współfinansowane będą inwestycje drogowe zlokalizowane na sieci dróg krajowych, w tym 4 inwestycje z zakresu dróg ekspresowych (S22 Elbląg-Grzechotki, S8 Radzymin - Wyszków, S1 Pyrzowice - Podwarpie, S5/S10 Bydgoszcz-Stryszek-Białe Błota)
- Conadrogach.pl7 Oct 2018StatusStageDelivery
Status · Stage · DeliveryOdcinek drogi ekspresowej S22 Elbląg – Grzechotki oddano do użytku jesienią 2008 roku. Przebudowa drogi krajowej nr 22 do parametrów trasy ekspresowej na 50 km fragmencie trwała blisko dwa lata i kosztowała 482 mln zł.
- Rynek Infrastruktury12 Sep 2025StageStatus
Stage · Statusdroga ekspresowa S22 na dwóch odcinkach: Elbląg Wschód – Granica, OUD Wielkie Wierzno, a także Elbląg – Grzechotki, OUD Wielkie Wierzno