S3 Expressway Nowa Sól – Legnica (Kaźmierzów – Legnica section)

completedstage: operationaldelivereddelayed
PLN 2.0 billion
programme budget (multi-year) · data from 2015net or gross: not recorded≈ PLN 2.0 billion (value-by-stage, est., nominal)funding: EU funds

The Kaźmierzów – Legnica section of the S3 expressway, approximately 48 km long, was the longer of the two parts of the S3 Nowa Sól – Legnica corridor, which carries the S3 route through the Copper Belt (Zagłębie Miedziowe) and connects it to the A4 motorway near Legnica. The investment was divided into tasks: Kaźmierzów – Lubin Północ (approximately 14.4 km), Lubin Północ – Lubin Południe, i.e. the Lubin bypass (approximately 11.3 km), and Lubin Południe – Legnica II / A4 interchange (approximately 22.6 km). Contracts with contractors were signed at the turn of 2014 and 2015 (including the Salini, Mota-Engil and Budimex/Ferrovial consortia), and the works were carried out under a design-and-build system. The EU co-financing agreement was concluded on 29 September 2015. The project was planned for 2015–2018, and the first sections were brought into service in that period: on 25 June 2018 the approximately 24-kilometre Lubin Południe – Legnica Południe fragment (with the connection to the A4), and on 27 August 2018 the approximately 10-kilometre Lubin bypass (Lubin Północ – Lubin Południe). The last fragment of the scope, Kaźmierzów – Lubin Północ (over 14 km), was brought into service in 2021: 6 km between Polkowice and Lubin at the end of October, and the last 8 km from the Polkowice Północ interchange (formerly Kaźmierzów) on 10 November, i.e. approximately three years behind schedule. The total value of the Kaźmierzów – Legnica section was PLN 1,977,015,241.77, including EU co-financing of PLN 987,066,467.08. The neighbouring, northern section of the Nowa Sól – Kaźmierzów corridor (approximately 33.3 km, approximately PLN 803 million) was brought into use on 15 September 2018. The beneficiary and manager of the road is the General Directorate for National Roads and Motorways (GDDKiA).

How it went

Assessment: settled, as of 10 Sep 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one carries no assessment yet, one has an assessment with no confirmed quote. How to read this section

Deliverydelivered[5]
Scheduledelayed[5]

Timeline

Slip: about 3 years vs. the original date (given as a year)

  1. Announced29 Dec 2009
  2. Construction start2015
  3. Original date2018
  4. Delivery10 Nov 2021

Significance

The sections opened in 2018 connected Lubin to the A4 motorway near Legnica by expressway. A continuous S3 through the Copper Belt (Polkowice, Lubin), and further north to Zielona Góra, Gorzów Wielkopolski and Szczecin, was achieved only on 10 November 2021, when the last fragment of the Kaźmierzów – Lubin Północ section was opened. The S3 is the Polish part of the trans-European Baltic–Adriatic corridor, and the expressway bypass of Lubin diverted transit traffic out of the city centre.

Sources 6 · 3 independent · 4 archived

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Mapa Dotacji UE (mapadotacji.gov.pl)
    CostInvestorFunding
    Cost · FundingProject value 1 977 015 241,77 zł Co-financing from the EU 987 066 467,08 zł
    InvestorName of the beneficiary GENERALNA DYREKCJA DRÓG KRAJOWYCH I AUTOSTRAD
  2. Generalna Dyrekcja Dróg Krajowych i Autostrad
    AnnouncedConstruction startOriginal date
    Announced29 grudnia 2009 r. decyzja wydana przez Regionalnego Dyrektora Ochrony Środowiska we Wrocławiu
    Construction start · Original dateLata realizacji: 2015 – 2018
  3. Generalna Dyrekcja Dróg Krajowych i Autostrad
  4. Generalna Dyrekcja Dróg Krajowych i Autostrad2018
  5. conadrogach.pl (portal Drogi w Polsce)13 Nov 2021
    StatusStageDeliverySchedule
    Status · Stage · DeliveryNa trasie oddano ostatni fragment budowanej latami S3-ki pomiędzy Lubinem i Polkowicami.
    ScheduleOd środy, 10 listopada, bez przeszkód pojedziemy drogą ekspresową S3 od Szczecina w woj. zachodniopomorskim do Bolkowa w woj. dolnośląskim. To łącznie ok. 420 km. Zakończyły się prace na ostatnim 8 km fragmencie drogi ekspresowej S3 od węzła Polkowice Północ (dawniej Kaźmierzów) do węzła Polkowice Południe.
  6. Generalna Dyrekcja Dróg Krajowych i Autostrad
    DeliveryStatusStageSchedule
    Delivery · ScheduleData udostępnienia ciągu głównego 10 listopada 2021 r.
    Status · StageAktualny etap W użytkowaniu