A1 motorway Toruń Południe – Kowal (Czerniewice–Kowal section, part of the A1 Toruń–Stryków build)

completedstage: operationaldelivereddelayed
PLN 1.8 billion
contract value · data from 2010net or gross: not recorded≈ PLN 1.8 billion (value-by-stage, est., nominal)funding: EU funds

An almost 64-kilometre section of the A1 motorway from the Toruń Południe interchange (Czerniewice) to the Kowal interchange in the Kuyavian-Pomeranian Voivodeship, built by GDDKiA as part of the A1 Toruń–Stryków motorway and closing the missing fragment of the north-south corridor south of the concession-based Gdańsk–Toruń section. Construction contracts under the "design and build" system were signed on 17 June 2010: the Czerniewice–Odolion and Odolion–Brzezie sections (a combined approximately 34.4 km) went to the SRB Civil Engineering consortium for PLN 934 million, and the Brzezie–Kowal section (approximately 29.5 km) to PBG S.A. for PLN 857 million, with opening to traffic planned for 2012. Following contractor problems and the termination of part of the contracts, the works were completed under contracts concluded in 2013. On 21 December 2013 drivers were able to use the 45-kilometre Toruń Południe–Włocławek Zachód section, and on 30 April 2014 the last 19 km of the route from Włocławek to Kowal was opened; permanent traffic arrangements were introduced on 23 May 2014. The investment was co-financed from the EU Cohesion Fund under the Infrastructure and Environment Programme 2007-2013.

How it went

Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one carries no assessment yet. How to read this section

Deliverydelivered[7]
Scheduledelayed[7]
Utilisationin use[2]

Timeline

Slip: about 2 years vs. the original date (given as a year)

  1. Original date2012
  2. Delivery2014

Change history

  • 30 Apr 2014status: completedUdostępnienie ostatnich 19 km trasy od Włocławka do Kowala domknęło odcinek Toruń Południe–Kowal.
  • 30 Apr 2014stage: operational

Significance

The opening of the Toruń Południe–Kowal section closed the A1 motorway connection from the Tricity and the concession-based Gdańsk–Toruń section towards central Poland, creating a continuous motorway route on this fragment of the corridor. The route runs through the Kuyavian-Pomeranian Voivodeship, carrying transit traffic on the European north-south corridor (TEN-T). Construction, delayed against the original 2012 deadline due to contractor problems and the termination of part of the contracts, was ultimately completed in 2014.

Sources 7 · 3 independent · 7 archived

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Generalna Dyrekcja Dróg Krajowych i Autostrad (archiwum)8 Jul 2010
    CostOriginal dateInvestor
    Cost934 mln zł. 3. Brzezie – Kowal (29,5 km) Otwarcie ofert na budowę odcinka 3 nastąpiło 22.03.2010 r. Oferty (9) złożyły konsorcja firm hiszpańskich, portugalskich, niemieckich, polskich i austriackich. Kosztorys przewidywał, że wartość kontraktu wyniesie 1 371 mln zł. Wykonawcą odcinka będzie polsko – irlandzkie konsorcjum, z liderem PBG S.A., które złożyło najniższą ofertę – 857 mln zł
    Original dateOddanie do ruchu: 2012 r.
    InvestorPodpisanie umów na budowę autostrady A1 Toruń - Kowal
  2. Generalna Dyrekcja Dróg Krajowych i Autostrad (archiwum)
    StatusStageDeliveryFundingUtilisation
    Status · Stage · Utilisationobecny etap - w użytkowaniu
    Delivery30 kwietnia 2014 roku - udostępnienie 19 km trasy od Włocławka do Kowala
    FundingPrzedsięwzięcie było współfinansowane przez Unię Europejską ze środków Funduszu Spójności w ramach Programu Infrastruktura i Środowisko.
  3. Generalna Dyrekcja Dróg Krajowych i Autostrad (gov.pl)
  4. Inżynier BudownictwaMay 2014
  5. Wikipedia (pl)
    Delivery
    Delivery30 kwietnia 2014 r. oddano do użytku 20 km odcinka Włocławek Północ – Kowal.
  6. PortalSamorzadowy.pl30 Apr 2014
    StatusStageDeliverySchedule
    Status · Stage · DeliveryBrakujący 19-kilometrowy odcinek autostrady A1 Gdańsk-Łódź między Włocławkiem a Kowalem (Kujawsko-pomorskie) otwarto w środę po południu.
    ScheduleWcześniej planowano, że cały odcinek A1 Czerniewice-Kowal będzie gotowy we wrześniu 2012 r. Na początku września 2012 r. GDDKiA zerwała jednak kontrakty z dotychczasowymi wykonawcami ze względu na niewywiązywanie się z przyjętych zobowiązań.