A2 Motorway (Świecko–Poznań–Łódź–Warsaw section)

completedstage: operationaldelivered
funding: multilateral development bank, private finance, state special fund, EU funds

A key east–west road corridor linking the Polish-German border at Świecko through Poznań and Łódź with Warsaw, being the Polish segment of a European corridor (the E30 road). The Świecko–Warsaw route was completed for the UEFA EURO 2012 European football championship (2012). The western section Świecko–Nowy Tomyśl, 105.905 km long, whose construction began in July 2009, was opened to traffic on 1 December 2011 (ahead of schedule); it was delivered by the concessionaire Autostrada Wielkopolska II S.A., with the general contractor being A2Strada (Kulczyk Holding and Strabag AG). The Łódź–Warsaw section (from the Stryków interchange to the Konotopa interchange), approximately 90 km long, managed by GDDKiA, was made passable on 6 June 2012, just before EURO 2012, enabling drivers to use the entire A2 motorway between Warsaw and Łódź. The Świecko–Konin section is tolled and maintained by the concessionaire Autostrada Wielkopolska, while the Konin–Warsaw section is maintained by GDDKiA.

How it went

Assessment: settled, as of 19 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 3 carry no assessment yet. How to read this section

Deliverydelivered[5]

A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.

Timeline

  1. DeliveryJun 2012

Change history

  • 6 Jun 2012stage: operational
  • Jun 2012status: completedCompletion of the Świecko–Warsaw corridor before UEFA EURO 2012 – the entire A2 between Warsaw and the German border became passable.
  • Jul 2009stage: construction

Significance

The completion of the A2 motorway on the Świecko–Warsaw route ahead of UEFA EURO 2012 connected Warsaw and central Poland with the motorway network toward the border with Germany, creating the primary national east–west road corridor. The last missing element was the Łódź–Warsaw section (Stryków–Konotopa, approximately 90 km), managed by GDDKiA and made passable on 6 June 2012, the day before the tournament's opening ceremony; the western section Świecko–Nowy Tomyśl (105.905 km) had already been operational since 1 December 2011. The investment was carried out under a mixed model: the tolled concession section Świecko–Konin (concessionaire Autostrada Wielkopolska) and the government section Konin–Warsaw maintained by GDDKiA.

Sources 10 · 4 independent · 8 archived

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.

  1. GDDKiA (serwis archiwalny)
    InvestorStage history
    InvestorOdcinek zrealizowany został przez koncesjonariusza – AUTOSTRADA WIELKOPOLSKA II S.A. z siedzibą w Poznaniu.
    InvestorOdcinek zrealizowany został przez koncesjonariusza – AUTOSTRADA WIELKOPOLSKA II S.A.
    Stage historybudowa Odcinka II autostrady A-2 Świecko-Nowy Tomyśl rozpoczęła się w lipcu 2009 r.
  2. Money.plJun 2012
    Status
    StatusOd dzisiaj kierowcy, w tym kibice jadący na pierwsze w historii Polski Mistrzostwa Europy w piłce nożnej mogą korzystać z całej autostrady A2 pomiędzy Warszawą a Łodzią
  3. Inżynier Budownictwa
    Stage
    StageOddano do ruchu 105,9-kilometrowy odcinek autostrady A2 z Nowego Tomyśla do Świecka.The sentence covers the Nowy Tomyśl – Świecko section (105.9 km), the western part of the route; the Stryków – Konotopa section was completed on 6 June 2012.
  4. Wikipedia (pl)
    StageDeliveryStage history
    Stage · Delivery · Stage history6 czerwca 2012 oddano do użytku jako przejezdny odcinek C wraz z fragmentami sąsiednich odcinków B i D do węzłów Grodzisk Mazowiecki i Skierniewice.The sentence covers the last fragment of the Stryków – Konotopa route to open (section C with parts of B and D); the other sections opened on 23 May, 27 May and 3 June 2012 according to the same page.
  5. Wikipedia (en)
    Delivery
    Deliveryopened to traffic in May and June 2012, the last parts of it one day before the opening ceremony of UEFA Euro 2012
  6. GDDKiA (serwis archiwalny)
  7. Funding
    Fundingkredytu udzielonego przez Europejski Bank Inwestycyjny w kwocie 974 mln euro (ok. 62,5% wartości projektu)
    Fundingkredytów udzielonych przez 11 międzynarodowych banków komercyjnych w kwocie 394 mln euro (ok. 25,5% wartości projektu)
    Fundingwpłat akcjonariuszy koncesjonariusza w kwocie 186 mln euro, stanowiących ok. 12% całkowitych kosztów realizacji
  8. Funding
    FundingCo-financing from the EU 175 316 032,00 zł
  9. Funding
    FundingŹródła finansowania: KFD