Expansion of the Passenger Terminal at Kraków-Balice Airport (2013–2016)
Reconstruction and expansion of the passenger terminal at John Paul II International Airport Kraków-Balice, the second-busiest airport in Poland, carried out between 2013 and 2016. The works, which began on 11 April 2013 with the handover of the site to the general contractor, the Italian firm Astaldi S.p.A., included the construction of a new part of the terminal (about 33,000 m² of usable floor space, known as T4) and the reconstruction of the existing building, so that the terminal's total usable floor area grew to about 55,000 m² and its capacity to about 8 million passengers a year. The contract with Astaldi was worth PLN 368.88 million gross, while the total investment cost, including the baggage handling and control system and security screening equipment, was estimated at about PLN 412–415 million gross. The newly built part of the terminal was put into use on 28 September 2015, and phase II (the section linking the old and new buildings, and the renovation of the former baggage hall) was completed in July 2016, shortly before World Youth Day. Completion of the works had originally been planned for the end of March 2015, but the investment was delivered with delay. The airport is managed by Międzynarodowy Port Lotniczy im. Jana Pawła II Kraków-Balice sp. z o.o., part of the PPL (Polish Airports) Capital Group.
How it went
Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one carries no assessment yet. How to read this section
A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.
- Capacity or target
- ok. 8 mln pasażerów rocznie (2016)
- Unit
- pasażerowie / rok
Timeline
Slip: +16 mo. vs. the original date
- Construction start11 Apr 2013
- Original dateMar 2015
- DeliveryJul 2016
Significance
The expansion significantly increased the capacity of Poland's second-largest airport, and largest regional airport, raising the terminal's total usable floor area to about 55,000 m² and its capacity to about 8 million passengers a year. The new terminal was delivered partly to handle increased traffic ahead of World Youth Day 2016 in Kraków. The distinctive glass form of the new part of the terminal (designed by APA Czech Duliński Wróbel) became a new landmark of the Balice airport.
Sources 5 · 4 independent · 4 archived
Every fact on this card comes from the sources below. Next to each source – which fields it supports.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- Sztuka Architektury2015StageCostDelivery
Stage · Delivery28 września 2015 otwarto nowy terminal portu lotniczego w podkrakowskich BalicachThe sentence is about stage I (the new terminal, 28 September 2015); stage II was delivered in July 2016.
CostKoszt inwestycji: 412 mln zł brutto
- Polskie Porty Lotnicze S.A. (PPL)2016StatusDeliveryInvestorFundingStage
Status · DeliveryRok później, w lipcu 2016 roku – tuż przed Światowymi Dniami Młodzieży – oddano II etap inwestycji
InvestorMiędzynarodowy Port Lotniczy im. Jana Pawła II Kraków-Balice Sp. z o.o., spółka z Grupy Kapitałowej PPL
FundingInwestycje zostały sfinansowane ze środków własnych spółki, obligacji a także funduszy unijnych.
FundingRozbudowa terminalu finansowana była ze środków Funduszu Spójności w ramach Programu Operacyjnego Infrastruktura i Środowisko (projekt POIS.06.03.00-00-014/12 pn. „Port lotniczy w Krakowie – rozbudowa istniejącego terminalu pasażerskiego"), jego wyposażenie w infrastrukturę bezpieczeństwa ze środków Europejskiego Funduszu Rozwoju Regionalnego, również w ramach POIiŚ (projekt „POIS.08.04.00-00-002/09 pn.: „Wyposażenie rozbudowanego terminalu pasażerskiego MPL Kraków – Balice w urządzenia bezpieczeństwa").
StageRok później, w lipcu 2016 roku – tuż przed Światowymi Dniami Młodzieży – oddano II etap inwestycji, który obejmował wybudowanie fragmentu budynku łączącego stary i nowy obiekt oraz przebudowę dawnej hali odbioru bagażu.
- Money.pl2015
- Wikipedia (pl)Construction startOriginal dateUtilisation
Construction start11 kwietnia 2013 roku ruszyły prace związane z budową nowego terminalu pasażerskiego, przebudową istniejącego obiektu oraz modernizacją wewnętrznego układu portu lotniczego, które rozpoczęła firma Astaldi S.p.A
Original datePlanowany termin zakończenia prac ustalono na koniec marca 2015 roku
UtilisationRok 2018 skończył się nowym rekordem – lotnisko obsłużyło ponad 6,7 mln pasażerów
- Forsal.pl2016ScheduleDelivery
Schedule · DeliveryJak podkreślił w poniedziałek minister infrastruktury i budownictwa Andrzej Adamczyk, inwestycja została zakończona, mimo ponad 600 dni opóźnienia, dzięki temu będzie można rozliczyć środki unijne przyznane na ten cel.