🚆Transportstrategic

Modernisation of railway line E30/C-E30 Kraków – Rzeszów (Podłęże – Rzeszów section, stage III)

completedstage: operationaldelivereddelayed
PLN 4.7 billion
programme budget (multi-year) · data from 2012net or gross: not recorded≈ PLN 4.7 billion (value-by-stage, est., nominal)funding: EU funds, state funds

Modernisation of the international railway line E30/C-E30 on the Kraków (Podłęże) – Rzeszów section (nearly 140 km of track), carried out by PKP Polskie Linie Kolejowe S.A. as stage III in two phases: Phase I under the Operational Programme Infrastructure and Environment 2007-2013 (project POIiŚ 7.1-30) and Phase II under POIiŚ 2014-2020 (project POIiŚ 5.1-7). The indicative total cost of the whole project was estimated (in 2012) at PLN 4,672.08 million, of which the estimated amount of EU co-financing was to be PLN 2,181.02 million; most of the financing consisted of EU funds under POIiŚ. The scope of the investment included the modernisation of nearly 140 km of track together with a new type of overhead traction network, computerised railway traffic control equipment and telecommunications, and the rebuilding and construction of 139 viaducts, bridges and flyovers, with the line brought up to a speed of 160 km/h for passenger trains and 120 km/h for freight. The works were originally planned to be completed by the end of 2014; the main works on the Podłęże – Rzeszów section were completed in December 2017, and from 10 December 2017 the fastest passenger trains ran on this route at speeds of up to 160 km/h. Phase II (POIiŚ 5.1-7, value PLN 711.9 million) covered supplementary works carried out in subsequent years. Rynek Kolejowy described the undertaking as one of PKP PLK's largest investments in the south of the country.

How it went

Assessment: settled, as of Dec 2017. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one carries no assessment yet, one has an assessment with no confirmed quote. How to read this section

Deliverydelivered[2]
Scheduledelayed[5]

Timeline

Slip: about 3 years vs. the original date (given as a year)

  1. Original date2014
  2. DeliveryDec 2017

Change history

  • Dec 2017status: completedZakończenie zasadniczych prac na odcinku Podłęże – Rzeszów; od 10 grudnia 2017 r. prędkość do 160 km/h dla pociągów pasażerskich.
  • Dec 2017stage: operational

Significance

The modernisation raised the maximum speed on the Kraków – Rzeszów route to 160 km/h for passenger trains and 120 km/h for freight, and cut journey times along this route. The rebuilding of 139 viaducts, bridges and flyovers and the construction of grade-separated crossings improved traffic safety. The line forms part of the international E30/C-E30 rail corridor in the TEN-T network, linking Poland with Western Europe and, via Rzeszów and Medyka, with the country's eastern border, and was one of PKP PLK's largest rail investments carried out in southern Poland.

Sources 6 · 4 independent · 5 archived

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Inżynier Budownictwa25 May 2012
    CostOriginal dateFunding
    Cost · FundingOrientacyjny koszt całkowity projektu to 4672,08 mln zł, z czego szacunkowa kwota dofinansowania z funduszy Unii Europejskiej wyniesie 2181,02 mln zł.
    Original dateZakończenie prac przewidziano na koniec 2014 roku.
  2. Rynek Kolejowy3 Dec 2017
    StatusStageDelivery
    Status · DeliveryZakończenie zasadniczych prac na linii E30 na odcinku od Podłęża do Rzeszowa
    Stage · DeliveryOd 10 grudnia br. składy pasażerskie pojadą z prędkością maksymalną do 160 km/h
  3. PKP PLK S.A. – Mapa inwestycyjna
  4. PKP PLK S.A. – Mapa inwestycyjna
    InvestorFunding
    InvestorPKP Polskie Linie Kolejowe S.A.
    FundingWARTOŚĆ DOFINANSOWANIA Z BUDŻETU PAŃSTWA ** 70 316 903,60 PLN
  5. Bankier.pl / PAP8 Mar 2016
    Schedule
    ScheduleZadanie rozpoczęte pod koniec 2010 r. miało się zakończyć w 2015 r. Na opóźnienie miała wpływ przede wszystkim wielka liczba decyzji administracyjnych, które musieliśmy uzyskać, konieczność wykupienia około 3 tysięcy działek, a także nieprzewidziane, dodatkowe roboty, jak np. konieczność wzmocnienia podtorza na ok. 37 proc. długości trasy - wyjaśnił Pietrończyk.
  6. Rynek Kolejowy8 Mar 2016