Purchase of 35 Siemens Inspiro trains for the Warsaw Metro

completedstage: operationaldelivered
PLN 1.1 billion
contract value · data from 2 Feb 2011net of VAT≈ PLN 1.1 billion (value-by-stage, est., nominal)funding: multilateral development bank, local government

On 2 February 2011, Metro Warszawskie Sp. z o.o. signed a contract with the consortium of Siemens AG (Siemens Sp. z o.o., Siemens Österreich) and Newag SA from Nowy Sącz for the delivery of 35 six-car Inspiro trains (210 cars in total). The value of the contract was PLN 1,069,594,000 net (approximately PLN 1.3 billion gross including 23% VAT). According to Siemens, this was the largest order the company had ever received in Poland; part of the production was carried out at Newag's plants in Nowy Sącz, and the first ten trains were assembled at Siemens's factory in Vienna. The first train arrived at the Kabaty Technical and Stabling Station on 21 December 2012, the first two Inspiro trains entered passenger service on line M1 on 6 October 2013, and the last ordered train was delivered to Kabaty on 27 October 2014. The new rolling stock primarily served line M1 and the first section of metro line II (M2), opened in 2015.

How it went

Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet. How to read this section

Deliverydelivered[3]
Utilisationin use[3]
eksploatacja składów Inspiro w Metrze Warszawskim
Current
35 sześciowagonowych składów Inspiro dostarczonych i eksploatowanych na liniach M1 i M2 (2023)

Timeline

  1. Construction start2 Feb 2011
  2. Delivery2013

Significance

The 2011 contract was the largest single rolling-stock purchase in the history of the Warsaw Metro and, according to Siemens, the largest order the company had received in Poland up to that time. The 35 Inspiro trains (210 cars) nearly doubled the metro fleet and made it possible to increase service frequency on line M1 and to launch operations on the central section of metro line II, opened in 2015. The Warsaw Inspiro was the first deployment of this Siemens train family anywhere in the world, and a significant part of production was located at Newag's Polish plant in Nowy Sącz.

Sources 5 · 5 independent · 3 archived

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Forsal.pl2 Feb 2011
    CostInvestor
    CostWartość podpisanej umowy to 1 mld 69 mln zł netto
    InvestorMetro Warszawskie podpisało w środę umowę z konsorcjum Siemensa i Newagu
  2. Rynek Kolejowy2 Feb 2011
    Funding
    FundingPrzetarg finansowany jest ze środków Metra Warszawskiego, uzyskanych dzięki wieloletniej umowie wykonawczej z miastem stołecznym Warszawa o świadczeniu usług przewozowych środkami komunikacji zbiorowej - pociągami metra w latach 2009-2027.
  3. Historia Transportu Publicznego27 Sep 2023
    StatusStageConstruction startDeliveryUtilisation
    Status · DeliveryOstatni zamówiony skład zjawił się w Kabatach 27 października 2014 roku
    Stage · Delivery6 października 2013 roku na linii M1 pojawiły się dwa pierwsze Siemensy
    Construction startUmowa na nowe pociągi dla Metra Warszawskiego została podpisana dnia 2 lutego 2011 roku
    UtilisationPozostałe 15 kursuje na linii M1 /Kabaty – Młociny/.
    UtilisationSkłady te zostały zamówione z myślą o obsłudze linii M2 /Bemowo -Bródno/ i tam też przydzielono 20 pociągów.
    UtilisationNiemiecki producent zobowiązał się dostarczyć 35 składów o długości 6 wagonów.
    UtilisationOstatni zamówiony skład zjawił się w Kabatach 27 października 2014 roku.
  4. transportszynowy.pl
  5. Funding
    FundingUmowa dotyczy udzielenia kredytu na zakup taboru metra i pokrywa 30% kosztów zamówienia.