Construction of the S3 Expressway Gorzów Wielkopolski – Nowa Sól, Sulechów (Kruszyna interchange) – Nowa Sól section (second carriageway of the S3 and second carriageways of the Gorzów Wielkopolski and Międzyrzecz bypasses)
A POIiŚ 2014–2020 project carried out by GDDKiA, covering the construction of the second carriageway of the S3 expressway on the Sulechów – Nowa Sól section, as well as construction of the second carriageway of the Gorzów Wielkopolski bypass and the second carriageway of the Międzyrzecz bypass in the S3 corridor, with a total length of 61.61 km. The task was divided into 5 implementation sections: second carriageway of the Gorzów Wielkopolski bypass (11.25 km), second carriageway of the Międzyrzecz bypass (6.37 km), Sulechów – Zielona Góra Północ (13.39 km), Zielona Góra Północ – Niedoradz interchange (13.31 km), and Niedoradz interchange – voivodeship road No. 283 (17.29 km). The co-financing agreement with the Operational Programme Infrastructure and Environment was signed on 20 October 2015; the total project value under the agreement was PLN 1,335,544,653.74, with maximum EU co-financing of PLN 700,905,529.63 (approximately PLN 700.9 million). The last section, the second carriageway on the more than 17-kilometre fragment between the Niedoradz interchange and Nowa Sól, was brought into service on 20 December 2018, completing the full dual-carriageway cross-section of the S3 expressway in the Lubusz Voivodeship. The investor and beneficiary was the General Directorate for National Roads and Motorways (GDDKiA).
How it went
Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet, one has an assessment with no confirmed quote. How to read this section
Timeline
- Original date31 Dec 2020
- Delivery20 Dec 2018
Significance
Completion of the second carriageways on the Sulechów – Nowa Sól section and on the Gorzów Wielkopolski and Międzyrzecz bypasses closed the full, dual-carriageway cross-section of the S3 expressway in the Lubusz Voivodeship: more than 170 km of continuous high-speed route from Gorzów Wielkopolski, through Zielona Góra, to Nowa Sól. The section is part of the trans-European corridor (S3) linking the port in Świnoujście with the border with the Czech Republic.
Sources 4 · 2 independent · 2 archived
Every fact on this card comes from the sources below. Next to each source – which fields it supports.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. Three is normally the minimum, and this record is a documented exception: independent reporting covers its sections and stages rather than the whole the record spans, so it cannot corroborate the figures without misstating them.
- GDDKiA (serwis archiwalny)CostOriginal dateFunding
CostCałkowita wartość projektu: 1 335 544 653,74 PLN
Original dateData zakończenia realizacji projektu wg UoD: 31.12.2020
FundingMaksymalna kwota dofinansowania z UE: 700 905 529,63 PLN
- Ministerstwo Funduszy i Polityki Regionalnej (POIiŚ)20 Dec 2018StatusStageDelivery
Status · Stage · DeliveryDo ruchu została dziś oddana druga jezdnia na ponad 17-kilometrowym odcinku między węzłem Niedoradz a Nową Solą.
- [3]Budowa drogi ekspresowej S3 ... odcinek Sulechów (w. Kruszyna) – Nowa Sól (gov.pl/GDDKiA) ↗archived ✓GDDKiA / gov.pl
- [4]Budowa drogi ekspresowej S3 ... odc. Sulechów (w. Kruszyna) – Nowa Sól – Mapa Dotacji UE ↗archived ✓Mapa Dotacji UEInvestor
Investornazwa beneficjenta GENERALNA DYREKCJA DRÓG KRAJOWYCH I AUTOSTRAD