Construction of the S3 Expressway Gorzów Wielkopolski – Nowa Sól, Sulechów (Kruszyna interchange) – Nowa Sól section (second carriageway of the S3 and second carriageways of the Gorzów Wielkopolski and Międzyrzecz bypasses)

completedstage: operationaldelivered
PLN 1.3 billion
programme budget (multi-year) · data from 2015net or gross: not recorded≈ PLN 1.3 billion (value-by-stage, est., nominal)funding: EU funds

A POIiŚ 2014–2020 project carried out by GDDKiA, covering the construction of the second carriageway of the S3 expressway on the Sulechów – Nowa Sól section, as well as construction of the second carriageway of the Gorzów Wielkopolski bypass and the second carriageway of the Międzyrzecz bypass in the S3 corridor, with a total length of 61.61 km. The task was divided into 5 implementation sections: second carriageway of the Gorzów Wielkopolski bypass (11.25 km), second carriageway of the Międzyrzecz bypass (6.37 km), Sulechów – Zielona Góra Północ (13.39 km), Zielona Góra Północ – Niedoradz interchange (13.31 km), and Niedoradz interchange – voivodeship road No. 283 (17.29 km). The co-financing agreement with the Operational Programme Infrastructure and Environment was signed on 20 October 2015; the total project value under the agreement was PLN 1,335,544,653.74, with maximum EU co-financing of PLN 700,905,529.63 (approximately PLN 700.9 million). The last section, the second carriageway on the more than 17-kilometre fragment between the Niedoradz interchange and Nowa Sól, was brought into service on 20 December 2018, completing the full dual-carriageway cross-section of the S3 expressway in the Lubusz Voivodeship. The investor and beneficiary was the General Directorate for National Roads and Motorways (GDDKiA).

How it went

Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet, one has an assessment with no confirmed quote. How to read this section

Deliverydelivered[2]

Timeline

  1. Original date31 Dec 2020
  2. Delivery20 Dec 2018

Significance

Completion of the second carriageways on the Sulechów – Nowa Sól section and on the Gorzów Wielkopolski and Międzyrzecz bypasses closed the full, dual-carriageway cross-section of the S3 expressway in the Lubusz Voivodeship: more than 170 km of continuous high-speed route from Gorzów Wielkopolski, through Zielona Góra, to Nowa Sól. The section is part of the trans-European corridor (S3) linking the port in Świnoujście with the border with the Czech Republic.

Sources 4 · 2 independent · 2 archived

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. Three is normally the minimum, and this record is a documented exception: independent reporting covers its sections and stages rather than the whole the record spans, so it cannot corroborate the figures without misstating them.

  1. GDDKiA (serwis archiwalny)
    CostOriginal dateFunding
    CostCałkowita wartość projektu: 1 335 544 653,74 PLN
    Original dateData zakończenia realizacji projektu wg UoD: 31.12.2020
    FundingMaksymalna kwota dofinansowania z UE: 700 905 529,63 PLN
  2. Ministerstwo Funduszy i Polityki Regionalnej (POIiŚ)20 Dec 2018
    StatusStageDelivery
    Status · Stage · DeliveryDo ruchu została dziś oddana druga jezdnia na ponad 17-kilometrowym odcinku między węzłem Niedoradz a Nową Solą.
  3. GDDKiA / gov.pl
  4. Mapa Dotacji UE
    Investor
    Investornazwa beneficjenta GENERALNA DYREKCJA DRÓG KRAJOWYCH I AUTOSTRAD