S8 Expressway Konotopa – Powązkowska (Trasa Armii Krajowej, Warsaw)

completedstage: operationaldelivered
PLN 2.1 billion
contract value · data from 2008incl. VAT≈ PLN 2.1 billion (value-by-stage, est., nominal)funding: EU funds

An urban section of the S8 expressway, approximately 10.4 km long, in Warsaw, connecting the Konotopa interchange (junction with the A2 motorway and the S8 expressway heading west) with al. Prymasa Tysiąclecia and the existing Trasa Armii Krajowej. The route runs grade-separated through the western districts of the capital, with the Mory, Warszawska-Lazurowa and Prymasa Tysiąclecia interchanges, grade-separated railway crossings and numerous viaducts. The investor was the General Directorate for National Roads and Motorways (GDDKiA), and the works were carried out by the consortium of Budimex Dromex S.A. (leader), Strabag Sp. z o.o., Mostostal Warszawa S.A. and Warbud S.A. The construction contract was signed on 22 January 2008 for PLN 2,149,235,184.89 gross; the value of the works contract accounted for the bulk of the total project value of PLN 2,728,223,303.37. The project was co-financed from European Union funds under the Cohesion Fund (Operational Programme Infrastructure and Environment 2007–2013), with a maximum co-financing amount of PLN 1,573,726,046.51. Works under the contract were completed on the contractual deadline of 15 December 2010, and the section was opened to traffic on 19 January 2011.

How it went

Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one carries no assessment yet, one has an assessment with no confirmed quote. How to read this section

Deliverydelivered[1]
Scheduleon time[1]

Timeline

  1. Construction start22 Jan 2008
  2. Delivery19 Jan 2011

Significance

The Konotopa – Powązkowska S8 section completed the connection between the A2 motorway (from the Konotopa interchange) and Warsaw's Trasa Armii Krajowej and the city centre's ring road system, taking transit traffic heading west out of densely built-up areas. The grade-separated, dual-carriageway expressway through the western districts of Warsaw became one of the key sections of the city's express ring road and completed the S8 route in the Warsaw agglomeration area.

Sources 5 · 3 independent · 3 archived

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. GDDKiA (serwis archiwalny)
    StatusCostConstruction startDeliveryFundingSchedule
    Status · DeliveryZrealizowany odcinek został oddany do ruchu w dniu 19.01.2011 r.
    CostWartość: 2 149 235 184,89 PLN brutto
    Construction startData podpisania umowy: 22.01.2008 r.
    FundingMaksymalna kwota dofinansowania z UE: 1 573 726 046,51
    ScheduleRoboty na kontrakcie zostały zakończone w terminie umownym tj. w dniu 15.12.2010 r.
  2. GDDKiA (serwis archiwalny)20 Jan 2011
    Stage
    StageKierowcy mogą od dzisiaj korzystać z ponad 10 km nowej drogi
  3. Urząd m.st. Warszawy20 Jan 2011
    Investor
    InvestorDroga ekspresowa S8 (wybudowana przez Generalną Dyrekcję Dróg Krajowych i Autostrad) o długości ok. 10,4 km
  4. ISAP / eli.gov.pl (Dziennik Ustaw)9 Oct 2007