S8 Expressway, Walichnowy interchange – Łódź (A1) section (Wrocław – Łódź direction)
Construction of the S8 expressway on the section from the Walichnowy (Wieluń) interchange to the Łódź Południe (A1) interchange, carried out by the General Directorate for National Roads and Motorways (GDDKiA) in the Wrocław – Łódź direction. The main expressway section is 104.07 km long; the project delivered a total of 113–114 km of dual-carriageway expressway divided into nine construction sections. The co-financing agreement was signed on 31 August 2012, with the project completion deadline set at 31 December 2015. The individual sections were opened to traffic in stages in 2013–2014; the last section, connecting Sieradz with Łask, opened on 29 November 2014. The total project value was PLN 5,099,462,890, of which the maximum EU co-financing amount (European Regional Development Fund, Operational Programme Infrastructure and Environment 2007–2013) was PLN 3,418,062,388. The construction cost of the nine sections alone exceeded PLN 4.5 billion, and the last section (Sieradz – Łask) was built by the Dragados – Pol Aqua consortium.
How it went
Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet. How to read this section
- Current
- ok. 2 godz. po oddaniu trasy (2014)
- Capacity or target
- wcześniej nawet do 5 godz.
Timeline
- Original date2015
- Delivery2014
Significance
The opening of the Walichnowy interchange – Łódź (A1) S8 section to traffic shortened the journey from Wrocław to Łódź from as much as 5 hours (through numerous towns) to around 2 hours, completing the expressway connection between these two agglomerations. With a main route length of 104 km, nine construction sections and a total value exceeding PLN 5 billion, it was one of the largest road projects carried out in Poland under the EU's 2007–2013 financial perspective.
Sources 5 · 3 independent · 4 archived
Every fact on this card comes from the sources below. Next to each source – which fields it supports.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- Generalna Dyrekcja Dróg Krajowych i Autostrad (serwis archiwalny)CostOriginal dateDeliveryFunding
CostCałkowita wartość projektu: 5 099 462 890 PLN
Original dateData zakończenia realizacji projektu wg UoD: 31.12.2015 r.
DeliveryRoboty zasadnicze zostały ukończone w dniu 14.11.2014r.
FundingMaksymalna kwota dofinansowania z UE: 3 418 062 388 PLN
- Generalna Dyrekcja Dróg Krajowych i Autostrad (serwis archiwalny)29 Nov 2014StatusStageDeliveryUtilisation
Status · DeliveryW ramach projektu powstało aż 114 km 2-jezdniowej drogi ekspresowej
Stage · UtilisationObecnie przejazd z Wrocławia do Łodzi trwa jedynie ok. 2 godz.
- [3]Budowa drogi ekspresowej S8 na odcinku węzeł Walichnowy – Łódź (A1) – Mapa Dotacji UE ↗archived ✓Ministerstwo Funduszy i Polityki Regionalnej (mapadotacji.gov.pl)Investor
Investornazwa beneficjenta Generalna Dyrekcja Dróg Krajowych i Autostrad
- TVN2429 Nov 2014Status
StatusOd soboty kierowcy mogą pojechać nowym odcinkiem drogi ekspresowej S8.